Rocket Lab pushes Neutron’s first launch into 2027 after finding voids in a carbon composite tank dome

Rocket Lab has pushed the first flight of its Neutron rocket into 2027 after inspectors found tiny air pockets inside a freshly cured carbon composite dome for the rocket’s first stage fuel tank. The New Zealand-founded company told the United States securities regulator on Wednesday afternoon American time, Thursday morning here, that “the first launch is now anticipated to shift into next year”, according to its Form 8-K filing. A short media release attached to the filing said the inaugural launch “is now expected to occur in 2027”.

Neutron is the medium lift rocket Rocket Lab has been building since it was unveiled in 2021, and it has slipped before. According to Yahoo Finance, the company originally targeted a 2024 first flight, then moved it to mid 2025, then to 2026. As recently as 10 August, in its second quarter results release, Rocket Lab said “Production of the Stage 1 tank is currently aligned with the target delivery of Neutron to the launch pad in Q4 2026.” That window has now closed.

Advertisement

The explanation came from founder and chief executive Sir Peter Beck in a seven minute video update posted to the company’s investor site. Rocket Lab makes Neutron’s major structures from carbon composite, the same family of materials used in its smaller Electron rocket, and the first stage tank is so large that it cannot be cured in an autoclave, the pressurised oven normally used to squeeze the carbon layers together as the resin hardens. The company has instead developed its own out of autoclave curing cycles for the biggest pieces, including the domes that cap each end of the tank. Beck said that if that process is not perfect, voids can form between the layers of carbon fibre, which weakens the part.

That is what inspectors found when they checked the newly cured forward dome. Beck said the voids did not necessarily mean the dome would fail in flight, “but our practice is to proceed only when we believe the system has the appropriate margins”. He added, “Possible success isn’t our standard.”

Beck traced the problem to a design change made after an earlier setback. On 21 January the first Stage 1 tank ruptured during a hydrostatic pressure trial, a test that pressurises the tank with water to push it to its limits. Rocket Lab’s statement at the time said “Testing failures are not uncommon during qualification testing.” In the video Beck said that failure was caused by a manual hand layup process run by a third party, and that the company then switched to its automated fibre placement machine, which lays the carbon down by robot. The switch allowed the engineers to remove joints and thicken some sections of the domes for extra strength. The voids formed in exactly those thicker sections.

Advertisement

According to Beck, the team was able to reproduce the defect in testing, changed the manufacturing process to stop it recurring, and then ran the matching aft dome through the new process. He said that dome came out as the best quality composite dome the company has made. A replacement forward dome is now being built on the same machine.

Rocket Lab has not given a new launch date and Beck said he would rather show progress than name a date he might have to walk back. He set out three steps instead. The new forward dome has to be built and cured, then checked with ultrasonic testing to confirm there are no voids. The dome and the rest of the first stage then have to be assembled and put through hydrostatic and cryogenic test campaigns. Beck said the company expects the first two steps to be done before the first quarter of 2027 and the third within that quarter, after which it should be able to share a target date.

Advertisement

The sharemarket did not wait. Yahoo Finance reported that Rocket Lab shares fell as much as 14 per cent on Thursday in New York before closing down 6.6 per cent, on top of a 7.9 per cent fall on Wednesday before the update was released. The stock is down about 25 per cent this year and roughly 65 per cent below the 52 week high of US$151 it reached in May, by Yahoo Finance’s reckoning. Rocket Lab joined the Nasdaq-100 index in June, and Newswire looked in May at what New Zealand investors should know about the shares.

What makes Neutron matter is the business that is waiting for it. In March 2025 the United States Space Force selected Neutron for Lane 1 of its National Security Space Launch programme, a contract with a maximum value of US$5.6 billion over five years. Rocket Lab’s announcement of that selection described a rocket “Designed to deploy payloads up to 13,000 kg” and said the company would only become eligible to bid for individual national security missions once Neutron had flown successfully. At the time the first launch was scheduled for the second half of 2025. The second quarter results also listed a contract worth up to US$397 million including options to build satellites for a Space Force airborne target tracking programme, with those spacecraft due to launch on Neutron.

Beck argued in the video that the slow path is the right one for a rocket meant to fly often and be reused, saying the company is deliberately not rushing to the pad with a minimum viable product that would need requalifying again and again. He said the second and third Neutrons are already being built before the first has flown, and that there are new Neutron contracts the company expects to announce soon.

For New Zealand the direct effect is limited. Neutron will fly from Rocket Lab’s Launch Complex 3 at Wallops Island in Virginia, not from Mahia. The company’s New Zealand operation keeps running on Electron, which flew its 97th mission from Launch Complex 1 on the Mahia Peninsula on 26 September, its 18th launch this year. Electron was itself the world’s first carbon composite orbital rocket, and Beck pointed to it, the 3D printed Rutherford engine and the Mahia site as examples of problems the company solved that nobody had solved before. Neutron is a much bigger version of the same bet, and the company that began with an Invercargill apprentice now has to prove it can build the largest composite pressure vessel ever made without air in the walls.

Rocket Lab’s third quarter results, which last year came out in November, are the next scheduled chance for investors to hear how the new dome is curing. Do you hold Rocket Lab shares, or follow the launches from Mahia? Tell us in the comments how much patience you have left for Neutron.

This article was written by AI, briefed to report the facts, hopefully without some of the bias people bring to the job 🙂