The Australian company behind what would be one of New Zealand’s largest gold mines has agreed to hand over a stack of outstanding reports two weeks earlier than it had planned, after the panel weighing the application warned that the original timetable would get in the way of its work.
Santana Minerals told shareholders on Monday it would deliver the final consent conditions and supporting information for its Bendigo-Ophir gold project, north of Cromwell in Central Otago, by 28 August rather than the 11 September date it had previously given. The company also said it would not be seeking any further pauses, RNZ reported.
The change matters because the fast-track process runs on a statutory clock. The expert panel assessing the project has a 140 working day window to reach a determination, with a decision due by 29 October and a draft expected at least six weeks before that. Santana had earlier volunteered a pause while it worked through a 30 point request for information from the panel, and had signalled it would resume on 17 August with the extra material following in September.
Panel chair Matthew Muir KC warned that those timings would “considerably impede” the panel’s work and its ability to meet the statutory deadline, and asked the company to reconsider. Santana’s revised date pulls the handover back inside a window the panel says it can work with.
Chief executive Damian Spring said the finalisation of consent conditions in August would let the panel move into what he called substantive deliberations on its decision, the Otago Daily Times reported. He said the company remained confident the project was well positioned to receive a positive outcome and, subject to approvals, could begin development activities in early 2027.
The material Santana still owes the panel is substantial. It includes a social impact assessment, best case and worst case economic forecasts, a lizard protection plan and a series of other responses to the panel’s questions. Groundwater work has been among the areas the panel has pressed the company on, since conditions are hard to write when the baseline information is not yet in hand.
The company has now spent about $17.7 million on the fast-track process alone. Its own breakdown puts roughly $10.1 million into environmental and technical investigations, $4.7 million into legal and advisory services, $1.9 million into panel, Environmental Protection Authority and other regulatory fees, and $1 million into cultural values assessments. That is money spent before a single consent has been granted, and it is a useful gauge of what a project of this scale now costs to get through the door, even under a process designed to be quicker than the one it replaced.
The mine itself would be large by any New Zealand measure. The proposal centres on an open pit roughly 1,000 metres long and 850 metres wide, with three smaller satellite pits and a tailings dam in the Dunstan Mountains. Santana has described the deposit as the most significant single gold find in New Zealand in more than four decades, and its pre-feasibility work points to production of around 120,000 ounces of gold a year over a mine life of about 14 years.
The economic case the company puts forward is built on those numbers. Santana’s own assessments point to roughly 300 to 350 operational roles once the mine is running, at average salaries well above the regional norm, along with several billion dollars of revenue across the life of the project and more than a billion dollars in taxes and royalties. Those are the applicant’s figures rather than an independent verdict, and testing them is part of what the panel has been asked to do, which is why the best case and worst case economic forecasts still to be filed carry some weight.
The project has divided Central Otago since it first appeared on the fast-track list. Community group Sustainable Tarras, which says it has more than 3,500 supporters, opposes the mine and has raised concerns about the quality and availability of water, seismic activity and other natural hazards, the landscape and tranquility of the area, and the long term effects on the natural environment and on nearby communities. Supporters, including local business interests, see a long run of well paid work in a district whose economy leans heavily on horticulture and tourism. Thousands of pages of public submissions have been filed on both sides.
Bendigo-Ophir has already cleared one significant hurdle. In May the company got overseas investment consent for the land purchases behind the project, leaving the fast-track approval as the main gate still to pass. Details of the application, the panel’s minutes and the timetable are published on the government’s fast-track register.
What happens over the next month will be watched well beyond Cromwell. Bendigo-Ophir is among the biggest applications to run the full length of the fast-track process, and it has tested the central promise of the regime, which is that complex projects can be decided quickly without cutting the assessment short. The pause, the volume of information still outstanding and the panel’s warning about timing all suggest that speed depends as much on how ready an applicant is as it does on the law.
If the reports land on 28 August as promised, the panel will have about two months to weigh them, publish a draft and reach a final call. If they slip again, the October date starts to look difficult, and a decision that drifts towards Christmas would push any construction start further into 2027.
Do you think the fast-track process is striking the right balance on a project this size, and would you want to see the mine go ahead? Have your say in the comments below.