Luxon challenges NZTA to build New Zealand’s $1.8 billion Cambridge to Piarere expressway in 18 months rather than five years

Prime Minister Christopher Luxon has publicly challenged the Transport Agency to build the 16 kilometre Cambridge to Piarere expressway in 18 months rather than the five years the agency has budgeted, in an exchange he later described as a coaching conversation.

Luxon visited the site of the project’s planned Karāpiro interchange on Monday, 19 days out from the 7 November election, flanked by Transport Minister Chris Bishop and Waikato National candidates Louise Upston, Tim van de Molen, Tama Potaka and Ryan Hamilton. The Waikato Times reported the stop was the first of a day that ended with a supporters’ rally in Hamilton.

Advertisement

The four-lane extension of the Waikato Expressway from Cambridge to the State Highway 1 and State Highway 29 roundabout at Piarere is a Road of National Significance. It received $1.773 billion in Budget 2026 and the agency expects construction to take five years. Luxon questioned both figures in front of Transport Agency chief executive Brett Gliddon, saying the route was a standard piece of road.

“I don’t understand, for a standard road like this … how do I not get this job finished in 18 months?” Luxon said, according to RNZ’s report of the visit.

Gliddon told the Prime Minister the project had faced environmental constraints and that the timeframe was dictated by the earthworks required. He said five years was a “high level” projection and that contractors had already been challenged to bring it down. “We’re putting real pressure on them to think outside the box,” he said.

Advertisement

Luxon was not satisfied with that. “If we’ve got lizards and stuff we need to deal with, we ain’t gonna take five years to deal with that,” he said. He pointed to Israel and Canada as countries capable of building faster, and asked whether rules needed to change to allow round the clock construction. “There must be a better way we can do it, it’s a straight up project … go 24/7, get the lights up, get the heaters going,” he said. “I don’t wanna talk about it any more, I wanna get it done.”

Gliddon told RNZ afterwards that 18 months would be “a bit ambitious” but that he would do his best. He said Luxon’s comments were “not unfair … he’s right, we ultimately want to deliver infrastructure faster”.

Advertisement

When RNZ put it to Luxon that he had been critical of the agency, he rejected the word. “I wouldn’t call it critical,” he said. “If you heard me talking – I hope you did hear me talking – it’s actually me pushing the system to make sure the system is delivering great value and doing what it can do to make sure projects are getting done well and done faster.” He said challenging officials was his job. “That’s what we call a coaching conversation.” He added that Gliddon was doing an exceptional job, that “Brett’s one of my favourite guys”, and that the agency had improved its value for money over the past three years. He said New Zealand sat in the top 10 per cent of countries for infrastructure spending, which was why taxpayers deserved to see the agency pushed on cost.

Bishop, standing beside him, offered the Waikare Gorge realignment between Wairoa and Napier as evidence the agency could beat its budgets. Construction on that project, which includes New Zealand’s highest road bridge, began earlier this month. “[It’s] a very important bridge in the East Coast … came in something like $50 million under budget,” Bishop said.

The 18 month target sits a long way from the agency’s own published programme. When the tender process opened in July, the Transport Agency said the first section, upgrading the existing highway from the Cambridge southern interchange to south of Karāpiro, would be awarded in December 2026 with construction starting in early 2027. The second section, a new expressway across farmland from Karāpiro to Piarere with four bridges, was expected to be awarded in early to mid 2027. The agency put the total build at five to six years. On that schedule the road opens around 2032. On Luxon’s schedule it would open before the end of 2028, within the next parliamentary term.

The project has a long history. The Transport Agency first consulted on the route in 2016, and the agency’s board approved the detailed business case in 2021 under the previous Labour government. Upston, who is the Cambridge MP, said after the Budget that she knew “how gutting it was back in 2018 when it was cancelled”. Resource consents were granted in September 2025 and early works were approved in December 2025. When the Government phased its Roads of National Significance programme in July, Cambridge to Piarere was among the projects kept on the fast track while five other highways were slowed.

The cost has also drawn fire from the opposition. When the Budget funding was announced in May, Labour transport spokesman Tangi Utikere told the New Zealand Herald the project was “not a new road” and that “when it was costed in 2023 it was $1 billion cheaper”. Green transport spokeswoman Julie Anne Genter said the road had “been in the wings for a decade” and noted it was being paid for from general Crown funds rather than fuel taxes and road user charges. Bishop said the road was expected to cut deaths and serious injuries on the corridor by about 70 per cent and put its benefit to cost ratio between 2.7 and 3.1.

Luxon’s intervention landed on the same morning Infrastructure New Zealand chief executive Nick Leggett urged all parties to keep individual projects out of coalition agreements and to let the Infrastructure Commission rank them instead. Leggett said New Zealand ranked 37th of 38 OECD countries on infrastructure value for money and that stop-start decisions had cost an estimated $11.8 billion in paused and cancelled projects. He said the Roads of National Significance were far enough advanced not to worry him, describing them as “essentially construction-ready with the main outstanding constraint being funding”, but warned that “dropping new projects out of nowhere would be far more concerning”. He told RNZ he was “optimistic, but not confident” that the bipartisan infrastructure talks Luxon and Chris Hipkins promised in last week’s leaders’ debate would survive the campaign.

The exchange at Karāpiro shows how the Prime Minister wants to run on infrastructure delivery in the final weeks of the campaign. National’s pitch is that it has restarted roads the previous government shelved and will now squeeze the agencies building them. Labour’s pitch is that many of those roads were already in the pipeline and that their price tags have grown under this Government. Whether a contractor can be found to pour 16 kilometres of four-lane expressway in 18 months, lights and heaters included, is a question that will outlast election day.

If you are still deciding how to vote on 7 November, our voting tool lets you compare every party’s policies side by side, including their transport and infrastructure plans.

Should the Prime Minister be setting construction deadlines for the Transport Agency, and is 18 months realistic for a 16 kilometre expressway? Tell us what you think in the comments.